Longhui 220kV power transmission project2016-05-10
Project Name: Longhui 220kV power transmission project
Product type: 220kV Copper Cable 1x2500mm2 4.5KM
Date: 2012-2013
Project profile: Longhui 220kV power transmission and substation project includes 220Kv supporting line construction, engineering supporting line includes six lines, Tower Block 169, involving three Court Division, mountain community, Taohong town, Kitayama, Shihmen five towns 37 villages The whole project on December 25, 2012 to commence and the investment is 1.4809 billion.
220kV substation is located in Longhui County Court Division of the town purple Kawamura, construction land is 45.69 acres, the transformer capacity is 18 million KVA. It is the first intelligent substation within the scope of Shaoyang City, Hunan Province, and it is a fourth intelligent substation substation construction strictly follow the "unified planning, unified standards and building" smart grid construction principle, to achieve an intelligent device, the second network equipment and auxiliary systems intelligent. The station uses advanced, reliable, integrated, environmentally intelligent devices to all stations of digital information and communication platform for networking, information sharing, standardization of basic requirements, automate information collection, measurement, control, protection, metering and monitoring basic functions, and according to the need to implement the sequential control, intelligent adjustment and other advanced features, making the equipment more scientific and reliable condition-based maintenance to minimize operational errors and improve the safe operation of the substation level.
Longhui 220kV power transmission project was completed in July 2013 and formally put into operation by the power, three months ahead of schedule to complete all engineering tasks. "Economic development, power demand in advance." Longhui 220Kv power transmission project completed and strengthened the Longhui grid structure, improve the reliability of power supply, improve the quality of electricity back to Bandung 120 people, 15 years to meet the needs of Longhui load growth conducive the county's industrial and agricultural production development, while achieving intelligent substation construction Shaoyang city "zero" breakthrough, power grid construction also marks the Shaoyang officially entered a new era of intelligent, real project is a bright, rich engineering, happiness project .
Solutions
We won the tender to provide 4.5KM 220kV 1x2500mm2. .We provided good quality cable according to contract requirements and got the user’s inspection acceptance.